Timeline
| Month & Year | Key Event |
|---|---|
| November 2024 | Lease Signed |
| Winter 2024 | Design plans drafted, approved |
| March 2025 | Construction documents finalized. Request for contract bids |
| April 2025 | Groundbreaking, construction commences |
| April 2025 – February 2026 | Build-out of new space |
| February 2026 | Construction completion expected |
| Spring 2026 | Move-in |
| Summer 2026 | Some programs launch at new location |
| Fall 2026 | Official launch of all classes at new location |